How do you get a building permit in Türkiye?

Short answer: A building permit is issued by the municipality where the plot is located. First, the zoning certificate and a geotechnical survey are obtained; then the architectural, structural, electrical and mechanical drawings are prepared, a contract is signed with a building inspection firm and the file is submitted to the authority. Once the drawings are approved and the fees are paid, the permit is issued.
Güngören Urban Regeneration Project, Sönmez Design

What are the steps of the permit process?

01Documentsdeed, zoning02Surveyssoil, survey03Drawingsarchitecture + eng.04Applicationinspection, fees05Permitapproval & start
Diagram — The drawings rely on the zoning certificate and the geotechnical survey; the design cannot be finalised without these two documents.

Required documents

DocumentWhere to get itWhat it is for
Title deed recordLand registry office, e-DevletShows ownership and shareholders
Zoning certificateMunicipal zoning departmentStates FAR, height, setbacks and permitted use
Setting-out plan and level sectionCadastre, licensed survey offices, municipalityDefines the plot boundaries and road levels
Geotechnical reportGeological and geophysical engineersInput for foundation and structural design
Architectural drawingsArchitectPlans, sections, elevations and area calculations of the building
Structural, electrical and mechanical drawingsThe relevant engineersDesign of the structure and building services
Building inspection contractBuilding inspection firmTakes on the inspection of drawings and construction
Contractor and site manager documentsBuilding contractorDefine responsibility for construction

Municipalities and the type of building may require additional documents, such as a lift design, fire report, parking calculation, landscape design or opinions from other authorities. Get the municipality's current list before applying.

Permit validity

Under Türkiye's Zoning Law, construction must start within two years of the permit date and the building must be completed within five years. If work does not start or finish within these periods, the permit lapses and must be renewed. Substantial changes to the design after the permit is issued require an amendment permit.

After the permit: the occupancy permit

When construction is complete, the building is inspected for compliance with the permit and drawings, and a building use permit (iskan, or occupancy permit) is issued. Without it, the building cannot move to condominium ownership, and utility connections and sales are affected. Work that departs from the drawings is the most common reason the occupancy permit is delayed.

What slows the process down

  • Inconsistencies between the zoning certificate and the title deed or cadastral records.
  • Lack of agreement between shareholders.
  • Architectural and engineering drawings that do not match; the authority asks for corrections.
  • Late opinions from other bodies (heritage boards, highways, aviation and so on).
  • Applying with missing documents.

For how the permit drawings relate to the other stages, see our article on the architectural design process.

FAQ

Frequently asked questions

Where do you get a building permit?

From the municipality where the plot is located; outside municipal boundaries, from the provincial special administration or the relevant competent authority.

Which drawings are needed for a permit?

Architectural drawings together with structural, electrical and mechanical drawings. Depending on the building, lift, fire and landscape designs may also be required.

How long is a building permit valid?

Construction must start within two years of the permit date and the building must be completed within five years. Otherwise the permit lapses.

How long does it take to get a permit?

It depends on how long the drawings take to prepare and how long the authority takes to review them. A complete file and consistent drawings shorten the process most.

What happens if you build without a permit?

The building is sealed, an administrative fine is imposed and, if the building cannot be brought under a permit, a demolition order may be issued.

What is iskan?

The building use (occupancy) permit. It shows that the building was completed in line with its permit and drawings, and is required for condominium registration.